Which party is responsible for construction administration, evaluation services, certifying applications for payment, and final inspection of work?

Explanation:
Construction administration, evaluation services, certifying applications for payment, and the final inspection of work are duties handled by the Architect-Engineer. They act as the designer’s representative to oversee the project during construction, ensuring everything aligns with the contract documents. This includes reviewing submittals like shop drawings, issuing clarifications or changes as needed, and approving changes via change orders. They also certify the contractor’s payment requests, confirming that the work completed justifies payment. Through regular site visits and observations, they assess progress and conformance, determine when the work reaches substantial completion, and conduct the final inspection to confirm everything is finished and ready for closeout or occupancy. The other parties have different roles: the contractor performs the construction work, the owner funds and makes decisions with the architect’s guidance, and the building official enforces codes and issues occupancy permits, rather than handling administration or payment certification.

Construction administration, evaluation services, certifying applications for payment, and the final inspection of work are duties handled by the Architect-Engineer. They act as the designer’s representative to oversee the project during construction, ensuring everything aligns with the contract documents. This includes reviewing submittals like shop drawings, issuing clarifications or changes as needed, and approving changes via change orders. They also certify the contractor’s payment requests, confirming that the work completed justifies payment. Through regular site visits and observations, they assess progress and conformance, determine when the work reaches substantial completion, and conduct the final inspection to confirm everything is finished and ready for closeout or occupancy. The other parties have different roles: the contractor performs the construction work, the owner funds and makes decisions with the architect’s guidance, and the building official enforces codes and issues occupancy permits, rather than handling administration or payment certification.