What are the two phases of the Design stage?

Prepare for the CSI Construction Documents Technology Exam with engaging flashcards and multiple-choice questions. Each question includes helpful hints and explanations to ensure you're ready for your test!

Multiple Choice

What are the two phases of the Design stage?

Explanation:
The Design stage is split into two phases: Schematic Design and Design Development. In Schematic Design the goal is to explore concepts and establish the overall form, layout, and spatial relationships that meet the program requirements within site and budget constraints. It answers questions about what the building looks like and how it fits together, using rough plans and massing rather than detailed specs. Design Development then takes those concepts and develops them into a coordinated, more detailed plan. It refines drawings, selects building systems, materials, and assemblies, and resolves interfaces among consultants so everything fits together coherently. This progression moves from broad ideas to a defined design that can be documented in Construction Documents later. Other options refer to stages outside the Design phase: Programming and Site Selection occur before design; Feasibility Study and Budgeting are early planning activities; Construction Documents and Procurement come after the design is established for construction and purchase processes.

The Design stage is split into two phases: Schematic Design and Design Development. In Schematic Design the goal is to explore concepts and establish the overall form, layout, and spatial relationships that meet the program requirements within site and budget constraints. It answers questions about what the building looks like and how it fits together, using rough plans and massing rather than detailed specs. Design Development then takes those concepts and develops them into a coordinated, more detailed plan. It refines drawings, selects building systems, materials, and assemblies, and resolves interfaces among consultants so everything fits together coherently. This progression moves from broad ideas to a defined design that can be documented in Construction Documents later.

Other options refer to stages outside the Design phase: Programming and Site Selection occur before design; Feasibility Study and Budgeting are early planning activities; Construction Documents and Procurement come after the design is established for construction and purchase processes.