Under Fast Track, what construction approach is described?

Prepare for the CSI Construction Documents Technology Exam with engaging flashcards and multiple-choice questions. Each question includes helpful hints and explanations to ensure you're ready for your test!

Multiple Choice

Under Fast Track, what construction approach is described?

Explanation:
Fast Track relies on overlapping design and construction by using multiple prime contracts for different parts of the project. By splitting the work into separate prime contracts, design can continue while construction starts on early packages, shortening the overall schedule. This approach contrasts with traditional single-prime procurement, where one contractor handles all work after design is finalized, and with design-build, where one entity handles both design and construction. Lump-sum bidding is a pricing method, not the delivery approach. So the described method is construction with multiple prime contracts.

Fast Track relies on overlapping design and construction by using multiple prime contracts for different parts of the project. By splitting the work into separate prime contracts, design can continue while construction starts on early packages, shortening the overall schedule. This approach contrasts with traditional single-prime procurement, where one contractor handles all work after design is finalized, and with design-build, where one entity handles both design and construction. Lump-sum bidding is a pricing method, not the delivery approach. So the described method is construction with multiple prime contracts.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy