The Execution section includes which action?

Explanation:
Execution covers the actions needed to finish and hand over the work, preparing the project for occupancy. Post-installation cleaning fits here because it directly prepares spaces after installation by removing dust, debris, and residues and restoring surfaces to their intended finished state—closing out the construction phase in a ready-to-use condition. The other items belong to different aspects: budget balancing is about cost management, submittal approvals occur earlier in the process when shop drawings and data are reviewed, and insurance requirements are addressed in the contract’s risk and coverage provisions rather than in the execution activities.

Execution covers the actions needed to finish and hand over the work, preparing the project for occupancy. Post-installation cleaning fits here because it directly prepares spaces after installation by removing dust, debris, and residues and restoring surfaces to their intended finished state—closing out the construction phase in a ready-to-use condition. The other items belong to different aspects: budget balancing is about cost management, submittal approvals occur earlier in the process when shop drawings and data are reviewed, and insurance requirements are addressed in the contract’s risk and coverage provisions rather than in the execution activities.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy