Record drawings are

Prepare for the CSI Construction Documents Technology Exam with engaging flashcards and multiple-choice questions. Each question includes helpful hints and explanations to ensure you're ready for your test!

Multiple Choice

Record drawings are

Explanation:
Record drawings capture what was actually built by updating the original contract drawings to include every change made in the field. They are created by marking up drawings with field changes, substitutions, and corrections, so the drawings reflect the true completed condition of the project. This makes them the official record for future maintenance, renovations, and verification that the work matches the contract. Original approved drawings show what was planned before construction, not what happened in the field. Drawings showing only final as-built conditions omit the ongoing changes documented during construction. Graphic instructions to bidders are bidding documents, not construction records.

Record drawings capture what was actually built by updating the original contract drawings to include every change made in the field. They are created by marking up drawings with field changes, substitutions, and corrections, so the drawings reflect the true completed condition of the project. This makes them the official record for future maintenance, renovations, and verification that the work matches the contract. Original approved drawings show what was planned before construction, not what happened in the field. Drawings showing only final as-built conditions omit the ongoing changes documented during construction. Graphic instructions to bidders are bidding documents, not construction records.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy