Construction Change Directive is

Explanation:
Construction Change Directive is a written instruction that directs a change in the work and is issued before the contract sum or time has been adjusted. It keeps the project moving by requiring the change to proceed while the parties negotiate the actual price and schedule impact, with the directive itself including the proposed basis for adjustment. This is different from a typical change order, which is issued after agreement on the adjustment. It is not just a routine update, a stop-work notice, or a permit.

Construction Change Directive is a written instruction that directs a change in the work and is issued before the contract sum or time has been adjusted. It keeps the project moving by requiring the change to proceed while the parties negotiate the actual price and schedule impact, with the directive itself including the proposed basis for adjustment. This is different from a typical change order, which is issued after agreement on the adjustment. It is not just a routine update, a stop-work notice, or a permit.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy